Insulation was supposed to have been started 03/13 or 03/14. That did not happen due to a delayed material delivery. The insulation ended up actually taking place 03/16. Fortunately, insulation is a pretty fast job!

My husband ended up contacting the county to ask if the inspector could come out just a bit earlier and thankfully he did. The inspection was completed 03/20. We had to cover the fire sprinkler with insulation on our own, which we did, and that was cleared by the county 03/21.




04/13
The attic insulation was blown in today. This happened after drywall was hung and mudding/taping was going on.