Wednesday, April 4, 2018

Mudding/Taping and Texture

04/02
Equipment for Mudding/Taping has been dropped off.

04/03
Mudding/Taping has started. Garage door was installed! :D

04/08
As of today, the mudding is still going on. Slower process than expected.

04/11
MUCH slower process than expected. HiLine's contractor is using one person to do the mudding job. Not only that, he is working on two homes simultaneously. Don't get me wrong, he seems to be doing a great job (very clean, kind, and professional), but the staffing should be better planned...The new timeline is mudding until 04/18, texture after, and painting 04/25. We'll see!

04/19
Texture started and finished today. We used a humidifier, fans and heating to speed the drying process so painting can start tomorrow.